Project Management Professional (PMP)45 / 152
Question 45 of 152
Midway through a 14-month predictive infrastructure project, the technical lead—who holds deep undocumented knowledge of the legacy integration design—gives notice and will leave in three weeks. The project manager is concerned about continuity once this person departs. What should the project manager do FIRST to protect project continuity?