A project manager is leading a 12-month hybrid infrastructure project. During execution, a key regulatory change is announced that could affect several planned deliverables. The project manager notices that the risk register has not been updated since the initial planning phase three months ago, and the team continues to reference the original risk priorities. What should the project manager do FIRST?