Question 43 of 152

A project manager is leading a hybrid initiative with three parallel workstreams, each led by a different lead who has developed a subsidiary plan (scope, schedule, resources) somewhat independently. As the PM begins integrating these into a single project management plan, they notice the workstream plans use different assumptions about a shared testing environment and different milestone naming conventions. What should the PM do FIRST to integrate the planning activities effectively?