Project Management Professional (PMP)42 / 152
Question 42 of 152
During integrated planning for a hybrid project, the project manager discovers that the schedule baseline assumes a vendor deliverable will arrive in week 6, but the procurement plan shows the contract award will not complete until week 8. Both plans were developed by different subteams and approved separately. What should the project manager do FIRST?