Question 41 of 152
Midway through a 14-month predictive project, the project manager notices the team keeps encountering integration problems that a previous, similar project also faced. The organization has a lessons learned repository, but the current team has not consulted it since the project charter was approved. What should the project manager do to best ensure project continuity and avoid repeating past mistakes?