Question 40 of 152

A software product team has a 12-month roadmap with dozens of planned features. The sponsor is under pressure from the executive board to show tangible business returns within the first quarter. The product owner and team estimate that the full solution cannot be completed for at least eight months. What should the project manager recommend to best deliver business value under these circumstances?