Question 39 of 152
A project manager is leading a product development effort with two distinct parts: a hardware component that is subject to strict regulatory approvals with fixed compliance milestones, and a software component whose requirements are still evolving based on user feedback. The sponsor wants both parts delivered under one project and asks the PM to recommend how to structure the delivery approach. What should the PM recommend?