Question 38 of 152
A project manager is launching a large transformation program that spans three business units, each with its own director. Early in the project, decisions about scope trade-offs and budget reallocations are being made inconsistently, and some directors reverse choices made by others, causing rework. The project manager has a charter and a sponsor but no defined mechanism for cross-unit decisions. What should the project manager do FIRST to address this situation?