Midway through a two-year financial-services platform project, a government agency announces a new tax-reporting mandate that will take effect before the project's planned go-live. The mandate does not change the current project scope, but it creates a significant new market opportunity: institutions that can report under the new format quickly will gain a competitive advantage. The sponsor asks the project manager how the team should respond. What should the project manager do FIRST?