Question 35 of 152
Midway through a two-year initiative to build a proprietary customer analytics platform, a competitor releases a similar off-the-shelf product at a fraction of the projected internal build cost. The project sponsor asks the project manager whether the initiative still makes sense. What should the project manager do FIRST?