A project manager is developing the initial budget for a new product-development project during the early planning stage. Very little detailed design information is available, and the sponsor needs a rough order-of-magnitude cost figure quickly to decide whether to authorize the project. The PM has data from three similar past projects the organization completed. Which estimating approach should the PM use to produce this initial cost figure?