Question 31 of 152

A project manager on an agile team notices that during sprint planning, team members wait for the PM to assign each task before starting work. This slows the planning session and the team appears disengaged during execution. Deadlines are still being met, but the PM wants to increase ownership and accountability. What is the BEST action for the PM to take?