On a hybrid product-development project, the sponsor has publicly asked the project manager to empower key business stakeholders to make day-to-day acceptance decisions on delivered features. However, whenever a feature is ready for acceptance, the stakeholders defer every decision back to the project manager, causing delays and a growing backlog of un-accepted increments. What should the project manager do to genuinely empower these stakeholders?