🔥 3-day streak
Project Management Professional (PMP)22 / 152
Question 22 of 152

A project manager is halfway through a predictive construction project. The performance report shows a budget at completion (BAC) of $500,000, earned value (EV) of $200,000, actual cost (AC) of $250,000, and planned value (PV) of $240,000. The sponsor asks the project manager to forecast the total cost the project will require at completion, assuming the current cost performance trend continues for the remainder of the work. What should the project manager report?

Reviewed for accuracy · Report an issueNext question