A project team has been experiencing a high rate of rejected deliverables during the quality control inspection stage, which occurs at the very end of each production cycle. The project manager notices that reworking these defects is consuming a large portion of the budget and delaying the schedule. The sponsor asks the project manager to reduce these quality-related costs. What is the BEST approach for the project manager to take?