Project Management Professional (PMP)12 / 152
Question 12 of 152
During execution of a globally distributed hybrid project, the project manager discovers a critical technical defect that requires an immediate decision from the sponsor and two lead architects who are in different time zones. The next scheduled steering committee meeting is in five days, but the defect is blocking a release planned for tomorrow. What is the BEST communication approach for the project manager to take?