Project Management Professional (PMP)11 / 152
Question 11 of 152
During a hybrid project, the project manager notices that a senior operations director—whose department will be heavily impacted by the deliverable—consistently attends review meetings but rarely speaks up, offers no feedback, and delegates all decisions to a junior analyst. Other stakeholders are actively engaged. The project manager suspects this director's silent disengagement could create adoption risks later. What should the project manager do FIRST?