Project Management Professional (PMP)8 / 152
Question 8 of 152

A predictive project has just received formal acceptance of the final deliverable from the customer. The project used two external vendors under fixed-price contracts, and there are still open invoices and one unresolved claim with one vendor. The sponsor asks the project manager to close the project quickly so the team can be released. What should the project manager do FIRST?