A project manager has assembled a new cross-functional team drawn from five different departments. After two weeks, members are openly questioning each other's roles, competing for influence in meetings, and progress on early deliverables has stalled. The PM recognizes the team is in the storming stage of development. What is the BEST action for the PM to take to move the team toward higher performance?