Project Management Professional (PMP)4 / 152
Question 4 of 152
A distributed agile team has been working together for three months. During a recent sprint, several team members expressed frustration that decisions made in meetings are frequently revisited later, and that some members feel their input is dismissed. The project manager notices that the team's original working agreements were created quickly during kickoff and never revisited. What is the BEST action for the project manager to take to build shared understanding?