A project manager is delivering a new customer self-service portal. The business case projected a 20% reduction in call-center volume, but this benefit will only materialize over the 12 months following go-live, well after the project formally closes. The sponsor asks the project manager how the organization will ensure this projected value is actually achieved once the project team disbands. What should the project manager do?