A project team is building a large customer-facing platform under a predictive plan that schedules a single go-live in 14 months. Midway through planning, the sponsor expresses concern that competitors are moving quickly and that the business will see no return until the entire platform launches. The sponsor asks the project manager how the team could begin realizing benefits sooner without abandoning the overall delivery commitment. What should the project manager do first?