During a sprint, your development team reports they cannot progress on three high-priority stories because a required API from an external partner organization has not been delivered. The partner is outside your organization's reporting structure and has repeatedly missed informal commitments. The team is becoming frustrated and idle. What is the BEST action for the project manager to take?