Hard PMP practice questions
Challenge — multi-step scenarios, trade-offs, and subtle distinctions. 10 hard questions available — no sign-up, always free.
A project manager is leading the rollout of a new medical device software product that will be sold in three countries. During planning, the team discovers that the regulatory requirements in one country directly conflict with the requirements in another—one mandates data be stored locally, while the other requires centralized reporting to a foreign authority. The sponsor wants the product launched simultaneously in all markets. What should the project manager do FIRST?
A project manager is halfway through a predictive construction project. The performance report shows a budget at completion (BAC) of $500,000, earned value (EV) of $200,000, actual cost (AC) of $250,000, and planned value (PV) of $240,000. The sponsor asks the project manager to forecast the total cost the project will require at completion, assuming the current cost performance trend continues for the remainder of the work. What should the project manager report?
Midway through a two-year financial-services platform project, a government agency announces a new tax-reporting mandate that will take effect before the project's planned go-live. The mandate does not change the current project scope, but it creates a significant new market opportunity: institutions that can report under the new format quickly will gain a competitive advantage. The sponsor asks the project manager how the team should respond. What should the project manager do FIRST?
During integrated planning for a hybrid project, the project manager discovers that the schedule baseline assumes a vendor deliverable will arrive in week 6, but the procurement plan shows the contract award will not complete until week 8. Both plans were developed by different subteams and approved separately. What should the project manager do FIRST?
During a hybrid project, a project manager notices that whenever disagreements arise in team meetings, one experienced engineer consistently withdraws, stops offering opinions, and later complies silently with whatever the group decides—even when the engineer privately expresses concerns about the technical approach. The PM is worried this pattern is suppressing valuable input and creating hidden resistance. What is the BEST action for the PM to take?
A predictive construction project is running two weeks behind on the critical path. The sponsor insists the original deadline be met, and there is a small unallocated budget reserve. The delayed activities involve pouring and curing concrete foundations, which have fixed technical durations that cannot be overlapped with the framing that follows. The project manager needs to recover schedule. Which action is most appropriate?
A project manager is closing a fixed-price contract with a specialized software vendor. During the procurement audit, the vendor claims that two additional integration features they delivered fall outside the original statement of work and submits an invoice for the extra effort. The project manager reviews the records and finds that these features were verbally requested by a team member during a status meeting but were never processed as formal change requests. How should the project manager proceed?
During execution of a predictive infrastructure project, the risk owner reports that a previously identified risk—a rare regional power grid fluctuation that could corrupt data during nightly batch processing—has a low probability but would cause severe, irreversible data loss if it occurred. A backup generator and redundant storage solution would cost 8% of the remaining budget. The sponsor is cost-conscious. What is the project manager's BEST course of action?
During execution of a predictive infrastructure project, the project manager identifies that a specialized subcontractor has unexpectedly freed up capacity and could complete a critical work package two weeks early at no additional cost, which would let the project deliver a key milestone sooner and capture a market advantage. The PM lacks the internal expertise to guarantee this outcome alone. Which risk response strategy is the PM applying if they formally assign this work package to that subcontractor to ensure the early benefit is realized?
During a hybrid project, two team members repeatedly disagree about how to sequence integration work. Instead of escalating to you, they have started bringing every disagreement to you for a decision, expecting you to pick a winner. You want the team to develop the capability to work through these disagreements themselves. As the servant-leader project manager, what is the BEST long-term approach?