ITIL 4 Foundation138 / 167
Question 138 of 167
A mid-sized software company frequently deploys minor configuration updates to a well-understood internal application. These updates follow a clearly documented, repeatable procedure and have an established, low risk profile with a track record of successful deployments. The change enablement team wants to avoid requiring separate assessment and authorization for each of these routine updates while still ensuring they are properly controlled. Which approach best fits this situation?