Question 58 of 167

A change enablement practice at a mid-sized company requires seven separate approval steps for a routine (standard) change, even for changes that carry almost no risk. Team members frequently complain that the delays outweigh any benefit, and several approvers admit they simply rubber-stamp requests without reviewing them. Which ITIL guiding principle most directly advises the improvement team on how to address this situation?