🔥 3-day streak
ITIL 4 Foundation12 / 167
Question 12 of 167
A regional bank has completed its continual improvement analysis. The team has agreed on a clear vision, confirmed the current baseline of service performance, and defined the measurable target state they want to reach. Their next meeting is focused on determining the specific approach and outlining an improvement plan to achieve those targets. Which step of the continual improvement model does this meeting represent?
Reviewed for accuracy · Report an issueNext question