A data center operations team is preparing to install a single NVIDIA DGX H100 system (8x H100 SXM GPUs) into an existing rack. The facility's power and cooling team asks the AI infrastructure engineer what the most important electrical planning consideration is for this node. Which statement best reflects the correct planning approach for a DGX H100?