A regional insurance company must ensure its claims-processing application can resume within 8 hours of a data center outage. The application changes frequently, and business impact analysis sets an RPO of 4 hours. Leadership wants to minimize ongoing costs while still meeting these targets. The IT team is choosing between recovery site strategies. Which option BEST balances the recovery objectives with cost efficiency?