A regional flood destroys a company's primary data center. The business continuity team has already shifted critical customer-facing operations to a manual workaround so orders can still be taken. Now leadership wants to restore the full IT environment at the alternate site and bring systems back to normal. Which plan governs this specific effort to rebuild and restore the technology environment?