A large software development project has been underway for six months. During a steering committee meeting, the risk practitioner notices that numerous unapproved feature additions have been incorporated into the build, causing the schedule to slip and the budget to overrun. The project manager argues the changes were minor and improved the product. Which project management weakness is MOST directly responsible for this situation?