Question 132 of 150
A financial services firm is replacing its legacy loan-management system with a modern cloud-based platform. During the SDLC deployment phase, records must be migrated from the legacy database to the new system. The project team plans to go live immediately after loading the data. As the risk practitioner reviewing the cutover plan, which activity is MOST important to require before authorizing the go-live?