ISACA CRISC — Certified in Risk and Information Systems Control118 / 150
Question 118 of 150
A manufacturing company implemented a mitigation control to reduce the risk of unplanned downtime from aging equipment. Post-implementation testing shows the control reduced the likelihood significantly, but the residual risk still sits slightly above the stated risk tolerance. The plant is scheduled for a full equipment replacement in 18 months, which will eliminate the risk source entirely. What is the MOST appropriate next step for the risk practitioner to recommend?