ISACA CRISC — Certified in Risk and Information Systems Control104 / 150
Question 104 of 150

A risk analyst is reviewing a risk register that lists several separate entries: a data center power failure, a single ISP link outage, and a HVAC cooling system failure — each individually rated 'low' likelihood and 'moderate' impact. The analyst notes all three depend on the same aging on-premises facility and could plausibly occur together during a heat wave. What should the analyst do to most accurately represent the risk to management?