🔥 3-day streak
ISACA CRISC — Certified in Risk and Information Systems Control81 / 150
Question 81 of 150

A retailer's risk analyst is evaluating two data-related risks for the risk register. Risk A involves a rare but catastrophic breach of the entire customer database, estimated once every 20 years, with a loss of $10 million per occurrence. Risk B involves frequent minor payment-processing errors occurring about 40 times per year, each costing roughly $8,000. Management wants to know which risk should receive higher priority for treatment based on expected annual loss. Which conclusion should the analyst present?

Reviewed for accuracy · Report an issueNext question