🔥 3-day streak
ISACA CRISC — Certified in Risk and Information Systems Control70 / 150
Question 70 of 150
A risk analyst must quantify the potential financial loss from a proposed cloud migration where multiple variables — outage frequency, per-hour revenue loss, and recovery duration — each have wide ranges of uncertainty. Senior management wants a probability distribution of possible loss outcomes rather than a single point estimate. Which risk analysis technique is MOST appropriate?
Reviewed for accuracy · Report an issueNext question