🔥 3-day streak
ISACA CRISC — Certified in Risk and Information Systems Control66 / 150
Question 66 of 150

A risk manager is designing the monitoring dashboard for a payment processing platform. The IT operations team wants to include a metric that tracks the percentage of patches applied within the mandated 30-day window, arguing it demonstrates how well the control is functioning. The risk manager wants a separate metric that provides an early warning that unpatched systems could soon lead to a security breach. Which combination BEST reflects the correct use of these two metrics?