Question 40 of 150

A risk analyst must estimate the likelihood and impact of a rare but severe supply-chain disruption for which the organization has no historical loss data. Management wants to avoid the situation where a single dominant senior executive skews the group's estimates during a live workshop. Which risk analysis approach BEST addresses this concern?