ISACA CRISC — Certified in Risk and Information Systems Control26 / 150
Question 26 of 150

During a risk response review, a newly appointed control owner for a data-loss-prevention (DLP) system tells the risk committee that because the control is operating effectively, the associated data-leakage risk is now fully 'owned and closed' by their team. The risk manager wants to correct the misunderstanding before it is documented in the risk register. Which statement best clarifies the accountability relationship the risk manager should communicate?