A newly appointed information security manager inherits a program with a fixed annual budget and staff of five analysts. The organization has approved three initiatives for the year: deploying a data loss prevention (DLP) solution, launching an enterprise-wide phishing simulation program, and upgrading the legacy identity and access management (IAM) platform. Resources are insufficient to fully execute all three simultaneously. What should the security manager do FIRST to determine how to allocate the limited resources?