Question 140 of 148
During implementation of a new order-management system, the project team applied an emergency patch to fix a defect discovered in the pricing module just before go-live. The IS auditor is reviewing the test approach used before deploying the patch. Which testing activity is MOST important for the team to perform before releasing the patched system to production?