ISACA CISA — Certified Information Systems Auditor104 / 148
Question 104 of 148
An organization is replacing its legacy payroll system with a new cloud-based solution. The payroll director insists that no employee should ever receive an incorrect or delayed paycheck during the transition, and management is willing to accept higher operational cost and effort to guarantee this. Which changeover technique should the IS auditor expect the project team to recommend?