An IS auditor reviewing IT operations notices that a critical order-entry application has failed and been restored by the service desk six times over the past three months. Each time, technicians restart the application server and close the ticket as resolved within the SLA. The underlying cause of the failures has never been determined. Which process is MOST deficient and should be strengthened?