During the implementation phase of a new order-management system, an IS auditor observes that the project team has completed unit testing of individual modules and is preparing for the next testing stage. The team wants to verify that data passed between the newly coded order-entry module and the inventory module behaves correctly when the modules operate together. Which type of testing should the team perform NEXT to address this concern?