Question 139 of 169

A retail company is planning to migrate a large on-premises data warehouse and dozens of interdependent ETL jobs to Google Cloud. Leadership wants to minimize risk and avoid discovering unexpected integration issues late in the project. As the data engineer leading migration planning, what should you do FIRST before scheduling any workload cutover?