🔥 3-day streak
CompTIA Security+ (SY0-701)74 / 77
Question 74 of 77
A regional insurance company is designing its disaster recovery strategy. Management wants to be able to resume critical operations within 12 hours of a primary data center failure, but the CFO has rejected proposals for a fully staffed, always-on secondary facility due to the ongoing expense. The IT team needs a recovery site that has hardware and network connectivity pre-installed, with recent (but not real-time) data available for restoration. Which site type BEST meets these requirements?
Reviewed for accuracy · Report an issueNext question →