Question 23 of 150
A network engineer submits a change request to upgrade the firmware on the core switches during a maintenance window. The change advisory board reviews the request but sends it back, stating that one critical element is missing that must be documented before approval. This element describes the specific steps to return the switches to their previous working state if the firmware upgrade causes an outage. Which element is the board requiring?