Question 107 of 147
A critical vulnerability with an active exploit in the wild is discovered on a customer-facing payment application. The security team has a validated vendor patch ready to deploy. Organizational policy requires all production changes to pass through the weekly Change Advisory Board (CAB) meeting, which is five days away. What is the MOST appropriate action for the vulnerability manager to take?