Question 42 of 140

Your team ships a managed solution named 'SalesCore' to production. A critical bug requires an urgent field change, but the full development solution contains many in-progress, untested components you cannot release yet. You need to deploy only the single fixed component to production quickly, while preserving the ability to later roll the fix into the base solution. Which ALM action should you take?