Question 96 of 138

Your Scrum team uses Azure Boards with two-week sprints. During sprint planning, the product owner wants a data-driven way to decide how many story points to commit to the upcoming sprint, based on the team's demonstrated throughput over the last several completed sprints. Which Azure Boards analytics widget should you add to the team dashboard to best support this forecasting decision?